Renovation of the Morteratsch-Pontresina power station
Project description:
Planning, delivery, assembly and commissioning of all required hydraulic steel construction components.
Scope of delivery:
- Renovation of 4 rolling sluices
- Elastic spring weir
- Stoplog system (flood protection)
- Stoplog system (underground canal)
- Corrosion protection
- Weir flap
- Intake sluice
- Grit evacuation sluice
- Coarse screen
- Fine screen
- Stoplog closure